Cleveland Clinic

Taussig Cancer Center - Cleveland, Ohio

Cleveland Clinic

Completed: August 2015
Project Metrics: 377,000 Sqft – 2,362 Tons Structural Steel Fabrication – New Construction
Project Team: Joe McEndree, Project Manager
Ken Miller, Estimator
Cameron Baker, P.E., Fabricators Structural Engineer

Subcontract Type: Design Assist

Owner/Customer: Allegheny Health Network

General Contractor: Turner Construction

Design Team: Stantec, Le Messurier

Highlights:

  • Target Value Management and Open Book Accounting
  • 17 Months from schematic design to topping out
  • Seven floor roof-suspended and cambered vehicular porte-cochere