Case Studies

Mercedes-Benz Van Manufacturing Plant – Ladson, SC

Scope: 1.2M Sqft.- 13,481 Tons – Structural & Misc Steel Fabrication and Erection

Key Personnel: Joe McEndree + Nick Gann – Project Managers | Ken Miller – Estimator | Cameron Baker, P.E. – Fabricator’s Design/Build Engineer

Delivery: New Construction – Design/Build

Steel Completed: August 2017

General Contractor: WG Yates

Highlights

Sideplate Systems Bolted Special Moment Frames (SMFs)

Intensive design team partnering to deliver on aggressive schedule

Wexford Hospital, Allegheny Health Network – Wexford, PA

Scope: 339,400 Sqft – 3,015 Tons – Structural & Misc Steel Fabrication and Erection

Key Personnel: Ken Miller – Estimator | Cameron Baker, P.E. – Fabricator’s Design Assist Engineer

Delivery: New Construction – Design/Assist

Steel Completed: November 2019

Design Assist Team: HKS – Architect & Structural Engineer | Gilbane Building Company – General Contractor

Highlights

6-story two-way cantilever Vierendeel truss system

Design/Assist Delivery, early steel delivery

Intensive integrated BIM coordination

Target Value Management with GMP

Stadium Expansion, University of Notre Dame – South Bend, IN

Scope: 631,000 Sqft – 10,060 Tons – Structural & Misc Steel Fabrication & Erection

Key Personnel:  Zach Shue – Project Manager | Ken Miller – Estimator | Cameron Baker, P.E. – Fabricator’s Structural Engineer

Delivery: New Construction – Design/Bid/Build

Steel Completed: January 2017

Design Assist Team: SLAM Collaborative – Architect | SDI – Structural Engineer | Barton Malow – General Contractor

Highlights

Complex project site with multiple cranes

Demanding project schedule with complex precursor trade coordination

Under Construction
We’re still adding to this page, so be sure to check back soon!