Mercedes-Benz Van Manufacturing Plant – Ladson, SC
Scope: 1.2M Sqft.- 13,481 Tons – Structural & Misc Steel Fabrication and Erection
Key Personnel: Joe McEndree + Nick Gann – Project Managers | Ken Miller – Estimator | Cameron Baker, P.E. – Fabricator’s Design/Build Engineer
Delivery: New Construction – Design/Build
Steel Completed: August 2017
General Contractor: WG Yates
Highlights
Sideplate Systems Bolted Special Moment Frames (SMFs)
Intensive design team partnering to deliver on aggressive schedule




Wexford Hospital, Allegheny Health Network – Wexford, PA
Scope: 339,400 Sqft – 3,015 Tons – Structural & Misc Steel Fabrication and Erection
Key Personnel: Ken Miller – Estimator | Cameron Baker, P.E. – Fabricator’s Design Assist Engineer
Delivery: New Construction – Design/Assist
Steel Completed: November 2019
Design Assist Team: HKS – Architect & Structural Engineer | Gilbane Building Company – General Contractor
Highlights
6-story two-way cantilever Vierendeel truss system
Design/Assist Delivery, early steel delivery
Intensive integrated BIM coordination
Target Value Management with GMP






Stadium Expansion, University of Notre Dame – South Bend, IN
Scope: 631,000 Sqft – 10,060 Tons – Structural & Misc Steel Fabrication & Erection
Key Personnel: Zach Shue – Project Manager | Ken Miller – Estimator | Cameron Baker, P.E. – Fabricator’s Structural Engineer
Delivery: New Construction – Design/Bid/Build
Steel Completed: January 2017
Design Assist Team: SLAM Collaborative – Architect | SDI – Structural Engineer | Barton Malow – General Contractor
Highlights
Complex project site with multiple cranes
Demanding project schedule with complex precursor trade coordination